Chernobyl Construction Weaknesses

[复制链接]
查看: 1405|回复: 4
发表于 2010-9-15 14:30:53 | 显示全部楼层 |阅读模式
The following memorandum sent by IU. Andropov outlines construction failings at the Chernobyl Nuclear Power Plant and the inadequate monitoring of the condition of safety equipment.








40


Not for publication


Secret

21 Feb. 79 05363
Return to the General
Section of the Central
Committee of the CPSU

Central Committee of the CPSU




USSR COMMITTEE OF STATE SECURITY [KGB]
February 21, 1979 No. 346-A
Moscow

Construction Flaws at the Chernobyl Nuclear Power Plant [AES]

According to data in the possession of the KGB of the USSR, design deviations and violations of construction and assembly technology are occurring at various places in the construction of the second generating unit of the Chernobyl AES, and these could lead to mishaps and accidents.

The structural pillars of the generator room were erected with a deviation of up to 100 mm from the reference axes, and horizontal connections between the pillars are absent in places. Wall panels have been installed with a deviation of up to 150 mm from the axes. The placement of roof plates does not conform to the designer's specifications. Crane tracks and stopways have vertical drops of up to 100 mm and in places a slope of up to 8 degree.

Deputy head of the Construction Directorate, Comrade V. T. Gora, gave instructions for backfilling the foundation in many places where vertical waterproofing was damaged. Similar violations were permitted in other sections with the knowledge of Comrade V. T. Gora and the head of the construction group, Comrade IU. L. Matveev. Damage to the waterproofing can lead to ground water seepage into the station and radioactive contamination of the environment.

The leadership of the Directorate is not devoting proper attention to the foundation, on which the quality of the construction largely depends. The cement plant operates erratically, and its output is of poor quality. Interruptions were permitted during the pouring of especially heavy concrete causing gaps and layering in the foundation. Access roads to the Chernobyl AES are in urgent need of repair.

Construction of the third high-voltage transmission line is behind schedule, which could limit the capacity utilization of the second unit.

As a result of inadequate monitoring of the condition of safety equipment, in the first three quarters of 1978, 170 individuals suffered work-related injuries, with the loss of work time totalling 3,366 worker-days.

The KGB of Ukraine has informed the CPSU Central Committee of these violations. This is for your information.


Chairman of the Committee [KGB]
[signed]IU. Andropov
回复

使用道具 举报

发表于 2010-9-15 15:49:03 | 显示全部楼层
KGB-克格勃?



                          
"Nuclear is Unclear   " -- A confucian in confusion.
回复 支持 反对

使用道具 举报

发表于 2010-9-15 17:07:13 | 显示全部楼层
谢谢楼主 希望继续
回复 支持 反对

使用道具 举报

发表于 2012-8-25 09:29:43 | 显示全部楼层
有才的不在少数啊  
回复 支持 反对

使用道具 举报

发表于 2012-8-25 09:29:43 | 显示全部楼层
昨晚多几分钟的准备,今天少几小时的麻烦。  
回复 支持 反对

使用道具 举报

您需要登录后才可以回帖 登录 | 注册

本版积分规则

Copyright © 2008-2025 核电论坛 版权所有 
京ICP备20002920号-3
快速回复 返回顶部 返回列表