Detailed Construction Plan with over 5000 activities hasbeen developed, reviewed and refined by constructionexperts.Schedule is based on working 5 days/week, 10 hours/day.Inspections during second shift. Third shift and weekendsreserved as contingency.Nuclear Island construction is the critical path.Plan emphasizes pouring concrete as early as possible.Construction plan has been linked to 3D computer model,creating a 4D virtual reality construction planning tool.
AP1000 Construction Plan